In this article named “Types of Formwork,” we review the different types of formwork. You can classify formwork in two useful ways: by the concrete member, such as a foundation, wall, slab, beam, or column; and by the material or construction system that crews use to build and move the form.
In other words, formwork is more than the surface touching the concrete. Specifically, it is the complete temporary support system, including sheathing, bearers, walers, shores, ties, braces, hardware, and reshoring where required. Therefore, the correct type must give the specified shape and finish while safely carrying fresh-concrete pressure and all construction loads.
Types of Formwork by Structural Member
| Concrete member | What the form must do | Typical main parts | Main check |
|---|---|---|---|
| Foundation or footing | Hold the perimeter and any steps, pockets, or pedestal shape | Side sheathing, walers, stakes, braces, and ties where needed | Line, level, dimensions, bearing of braces, and resistance to uplift or movement |
| Wall | Resist lateral pressure between two large faces | Face panels, studs, walers, ties, braces, and cleaning openings | Tie pattern, plumbness, joint tightness, bracing, and pour rate |
| Slab | Support the wet slab, reinforcement, workers, and placing equipment | Decking, joists/bearers, stringers, shores, heads, sills, and braces | Shore capacity, base support, level, load path, stripping, and reshoring sequence |
| Beam | Support the beam bottom and contain lateral pressure at the sides | Bottom panel, side panels, walers, yokes/ties, shores, and bracing | Bottom support, beam width/depth, side restraint, and removal sequence |
| Column | Contain high lateral pressure around a small vertical section | Face panels, clamps/yokes, walers, braces, and a clean-out opening | Location, cross-section, plumbness, clamp/tie layout, and pour rate |
Foundation Formwork
First, engineers can design foundation formwork in various ways. Basically, there is a difference between formwork for individual foundations, such as pad or socket foundations, and formwork for strip foundations. Therefore, the form depends on the size and shape of the foundation and on how the crew supports the sides.
For example, crews arrange an individual-foundation form around a compact footing or pedestal. In contrast, strip-foundation formwork is long and continuous, so alignment and bracing along its length require particular care.
In practice, crews commonly use sheeting panels with bearers or walers. For example, bracing may include squared or round timbers and diagonally arranged boards. However, use tie wires or proprietary ties only where the design permits them. Finally, the braces must bear on a firm support and resist movement or uplift during placement.

Wall Formwork
For wall work, traditional formwork uses vertically arranged upright timbers or studs, and crews fix the sheeting on the concrete side. Alternatively, crews may use prefabricated sheeting panels instead of individual boards. Therefore, horizontal walers distribute the load, ties hold opposite faces at the specified spacing, and braces keep the assembly plumb and stable.
In addition, provide cleaning holes at the foot of the form where required. Therefore, joints must be tight enough to prevent grout loss, while ties, anchors, walers, and braces must follow the formwork drawings. Meanwhile, wind can govern wall-form bracing before crews place concrete.

Slab Formwork
For slab forms, the original training handbook uses the term ceiling formwork, which is common in building construction. For example, the sheathing may consist of boards or prefabricated panels. Then, secondary bearers transfer the load to main bearers and finally to shores, frames, or towers.
For smaller rooms, a main bearer and two shores may form a trestle. In addition, diagonal bracing resists horizontal forces. Traditional timber shores may stand on double wedges that help with level adjustment and controlled stripping. However, although modern systems use engineered heads, props, frames, or table forms, the load path must remain continuous down to a firm support.

Beam Formwork
For beams, formwork normally has a bottom panel and two side panels that match the dimensions on the project drawings. Before erection, crews may prefabricate traditional panels on a preparation table.

Next, crews may place the bottom panel on a pedestal support or on shores carrying a waler. Then, they erect the side panels on the bottom and hold them with thrust boards, walers, yokes, ties, or other designed hardware. In addition, stulls or spacers may keep the projected beam width during assembly, but any item left in or passing through the concrete must comply with the drawings and specification.
However, the minimum bottom-panel width is not a universal number. It depends on the specified beam width, the thickness and arrangement of the side panels, and the selected support detail.

Column Formwork
Similar to beam forms, crews may prefabricate traditional column sheathing to the column dimensions from boards connected by cover straps. Next, they set the panels at the exact column location and hold them with clamps, yokes, walers, or proprietary ties. Therefore, diagonal braces keep the form plumb and provide provisional stability.
However, the formwork design specifies clamp spacing; do not assume a typical number because pressure changes with column size, concrete consistency, temperature, rate of placement, and method of consolidation. Also, provide a clean-out opening at the foot so crews can remove debris before concrete placement.
For example, when crews erect reinforcement within a traditional box form, they may install two adjacent sides first to allow access. Then, they fit the remaining sides after checking the reinforcement and cover devices.

Types of Formwork by Material and System
The member name tells us which concrete member the form creates. In contrast, the material or system tells us how crews build, handle, reuse, and move the form. A system may combine several materials; for example, a steel or aluminium frame may carry a plywood or composite face.
Panel form materials
| Type | Best fit | Main advantage | Main limitation or check |
|---|---|---|---|
| Site-built timber or plywood | Small jobs, irregular shapes, and one-off details | Easy to cut and adapt on site | Workmanship, moisture, damage, limited reuse, and variable material properties |
| Steel-framed panel | Repeated walls, columns, and heavy-duty work | High stiffness and many reuses when maintained | Weight, crane or handling needs, corrosion, joints, and repair of the face |
| Aluminium-framed panel | Repeated building layouts and fast floor cycles | Lower unit weight and consistent geometry | Proprietary layout, careful handling, repair limits, and early planning for openings |
| Plastic or composite panel | Repeated simple shapes and wet or corrosive exposure | Lightweight and easy to clean for suitable systems | Temperature, stiffness, connection details, damage, and manufacturer limits |
Moving and permanent form systems
| Type | Best fit | Main advantage | Main limitation or check |
|---|---|---|---|
| Table or flying form | Large repetitive floor plates | Moves a slab bay as one large unit | Edge protection, crane/movement plan, stability, and reshoring sequence |
| Tunnel form | Repetitive cellular buildings | Casts walls and slab together in a regular cycle | Layout must suit repetition; services and openings need early coordination |
| Climbing or jump form | Cores, shafts, piers, and tall walls | Moves vertically with the structure | Anchorage, wind, working platforms, sequencing, and engineered operation |
| Slipform | Continuous tall walls, silos, shafts, and similar sections | Continuous placing without conventional stripping cycles | Continuous supply, controlled lift rate, geometry, jacking, and specialist supervision |
| Stay-in-place form | Applications where the contractor intentionally leaves the form as part of the assembly | Removes a stripping operation and may add another function | Compatibility, durability, fire, bond, drainage, and specification requirements |
For a deeper material discussion, see formwork materials. In addition, see lumber formwork for timber selection and North American size terminology.
How to Select a Formwork Type
However, the cheapest face material is not always the lowest-cost formwork system. Therefore, selection should consider the member geometry, number of repetitions, required finish, concrete pressure, available labour and lifting equipment, cycle time, access, weather, and the planned stripping and reshoring sequence.
- First, start with the structural geometry, pour sequence, construction joints, openings, and required finish.
- Next, define the loads and concrete-placement conditions. Therefore, review loads on falsework and formwork rather than assuming that all walls or slabs create the same demand.
- Then, compare the number of reuses against fabrication, handling, cleaning, repair, and storage cost.
- After that, check how the crew will erect, brace, access, strip, move, and reshore the system without an unstable intermediate condition.
- Finally, use the approved formwork drawings and the system manufacturer’s instructions. Therefore, the responsible qualified person must review field substitutions.
Pre-Pour Check
- First, confirm that dimensions, line, level, plumbness, camber, joints, and openings agree with the drawings.
- Next, confirm that sheathing, bearers, walers, ties, anchors, braces, shores, sills, heads, and connections are complete.
- Then, verify that the support below is firm, stable, and able to carry the intended load.
- After that, use and secure the clean-out openings, and remove debris and standing water.
- Also, confirm that the release agent is compatible and has not contaminated reinforcement or construction joints.
- Finally, agree on access, working platforms, edge protection, pour rate, equipment position, and inspection responsibilities before placement.
References
- ACI PRC-347-14(21), Guide to Formwork for Concrete.
- OSHA 29 CFR 1926.700, Scope and definitions.
- OSHA 29 CFR 1926.703, Requirements for cast-in-place concrete.
- The Concrete Society, Formwork shape.
- Hu et al., A review of formwork systems for modern concrete construction.
The published article retains these existing diagrams and credits Formwork Making – Course: Timberwork Techniques, Trainees’ Handbook of Lessons (IBE, Deutschland). The site owner should verify reuse rights and attachment metadata.