Underwater concrete has been used for a long time. The act of placing fresh concrete below water without first dewatering the whole placement area is called underwater concreting.
As you can imagine, underwater concreting imposes more restraints than casting concrete in normal conditions. Fresh concrete must reach its position without excessive washout, dilution, segregation, or interruption.
Does Concrete Set Under Water?
Yes. Portland cement and other hydraulic cements harden by hydration, so they do not need to dry in air. The difficulty is the placement stage: moving water can dilute or wash out fresh paste before the concrete has set. Once a sound mass is in place and left undisturbed, immersion itself does not stop hydration.
Where Underwater Concrete Is Used
Underwater concrete is used for bridge piers, quay walls, harbours, offshore structures, marine repairs, drilled shafts, foundations below the groundwater level, and seal slabs in cofferdams.
It is not one fixed mixture for every application. The mixture and placement method are selected together according to depth, water movement, reinforcement congestion, required strength, durability exposure, and available equipment.
Main Risk During Placement
The main problem is direct contact between flowing water and fresh cement paste. Water can wash cementitious material away, change the water-to-cementitious-material ratio, and cause laitance or weak zones. The objective is to place a continuous mass while keeping the discharge point protected inside fresh concrete.
Tremie Method of Underwater Concreting

A tremie is a watertight pipe with a hopper at the top. Concrete flows through the pipe by gravity. At the start, a plug, pig, valve, or other approved arrangement separates the first concrete from the water inside the pipe.
- Position the tremie near the lowest part of the placement.
- Seal the discharge end or use the approved starting device so that the first concrete is not diluted inside the pipe.
- Fill the pipe and establish the initial concrete seal.
- Continue the placement without unnecessary interruption.
- Raise the pipe gradually as the concrete level rises, while keeping the outlet embedded in the fresh concrete.
- Monitor the concrete level, delivered volume, tremie position, and any sign of blockage or loss of seal.
The exact pipe diameter, outlet embedment, spacing, and starting procedure belong in the project method statement. FHWA’s November 2024 bridge-repair manual describes tremie and pumped placement, including careful monitoring and maintenance of the seal.
Required Properties of the Concrete
- High flowability: the concrete must move around reinforcement and into the form without normal internal vibration.
- Cohesion: the mixture must resist segregation while flowing.
- Washout resistance: cement paste and fines must not disperse easily into the surrounding water.
- Controlled bleeding: excessive water movement can create channels and weak layers.
- Suitable setting time: the concrete must remain workable for the expected placement duration without creating cold joints.
- Durability: permeability, cover, cementitious system, and exposure requirements must suit the water and soil environment.
Water reducers and, when specified, anti-washout admixtures can improve flow and cohesion. Their dosage is established by trial mixtures and the manufacturer’s data, not by applying one universal percentage range.
Methods of Underwater Concreting
| Method | How it works | Main control point |
|---|---|---|
| Tremie | Concrete flows by gravity through a watertight pipe | Keep the outlet embedded and the placement continuous |
| Pumped concrete | A pump pushes concrete through a watertight line | Maintain a protected discharge and avoid line blockage |
| Bottom-opening bucket | A closed bucket carries concrete to the placement level and opens near the surface | Limit exposure and disturbance while releasing each batch |
| Preplaced aggregate | Clean coarse aggregate is placed first, then grout is injected from the bottom upward | Fill voids completely and maintain grout flow |
| Bagged concrete | Bags of suitable concrete or mortar are placed for limited repair or protection work | Not normally suitable for a large monolithic structural placement |
| Dewatered cofferdam or caisson | Water is excluded and concrete is placed in a controlled dry or nearly dry space | Control seepage, uplift, stability, and water ingress |
Before the Pour
- Approve the trial mixture, placing method, sequence, and contingency plan.
- Inspect formwork for leakage and provide a path for displaced water.
- Confirm reinforcement spacing allows the selected concrete to flow.
- Check the tremie or pump line for clean, smooth, watertight joints.
- Confirm that enough concrete can be supplied for a continuous placement.
- Establish reference levels and a method to measure the rising concrete surface.
- Prepare backup equipment and a response for blockage, delay, or loss of seal.
Quality Control During Placement
- Test fresh concrete at the required frequency for slump or slump flow, temperature, air content, and unit weight where applicable.
- Record truck or batch times and the quantity placed.
- Measure concrete elevation at several locations and compare it with the theoretical volume.
- Observe displaced water for unusual cement clouding that may indicate washout.
- Do not lift the discharge outlet out of the fresh concrete.
- Overplace or remove contaminated surface concrete where the specification requires it.
Common Underwater Concrete Defects
| Defect | Likely cause | Prevention |
|---|---|---|
| Washed-out paste or laitance | Direct contact with moving water or lost discharge seal | Keep concrete isolated and control the outlet |
| Segregation | Unsuitable mixture, excessive fall, or poor flow control | Use a verified cohesive mixture and approved placement procedure |
| Cold joint | Supply interruption or early loss of workability | Plan continuous supply and suitable setting time |
| Voids around reinforcement | Congestion, blocked flow path, or insufficient spread | Coordinate bar spacing, aggregate size, and mixture flow |
| Weak top layer | Contaminated first concrete, bleeding, or trapped laitance | Overplace and remove unsound surface material as specified |
References and Related Articles
- FHWA-NHI-23-029, Underwater Bridge Repair, Rehabilitation, and Countermeasures Reference Manual, November 2024.
- ACI PRC-546.2-20, Guide to Underwater Repair of Concrete.
- ACI PRC-304-00, Guide for Measuring, Mixing, Transporting, and Placing Concrete (Reapproved 2009).
- PCA, Design and Control of Concrete Mixtures, 16th edition.
- Types of Concrete Admixtures.
- Cohesiveness and Consistency of Concrete.