Information for Ordering Concrete

Concrete pump

Ordering ready-mixed concrete is a coordination task, not only a quantity calculation. The supplier needs enough information to confirm the mixture, delivery rate, access, and discharge plan. The purchaser must also check the project specification and delivery ticket. Terminology, minimum loads, order increments, returned-concrete charges, and permitted site adjustments vary by supplier and jurisdiction.

Information to give the concrete supplier

Information What to confirm
Project and placement Site address, contact, placement element, date, start time, and expected duration
Quantity Total volume, planned loads, supplier increment/minimum, and procedure for a final balance load
Mixture designation Project mixture ID or complete performance/prescriptive requirements under the applicable specification
Fresh properties Required slump or flow, air content where specified, maximum aggregate size, temperature limits, and any placement-specific needs
Exposure and performance Strength class, exposure class, durability limits, cementitious restrictions, and test/acceptance requirements
Delivery logistics Truck access, height/weight limits, washout, pump or chute, truck spacing, unloading rate, traffic control, and communication
Special requirements Fibers, pigments, admixtures, hot/cold-weather plan, restricted materials, or environmental product documentation

Calculate concrete volume

Use consistent dimensions and calculate the net geometric volume for each element. For a rectangular slab:

Volume = length × width × thickness

Example: a slab is 12.0 m long, 7.5 m wide, and 0.15 m thick.

Volume = 12.0 × 7.5 × 0.15 = 13.5 m³

In inch-pound units, calculate cubic feet and divide by 27 to obtain cubic yards. For complex geometry, split the work into simple shapes, deduct large openings only when appropriate, and check the result against drawings or a quantity model.

Choose an allowance based on project risk

The order quantity is not always the exact geometric volume. Subgrade irregularity, form movement, over-excavation, embedded items, spillage, pump-line filling, and measurement tolerance can change demand. There is no universal “always add 10%” rule. Agree on an allowance based on survey accuracy, element geometry, placement method, historical data, supplier increments, and the cost of shortage versus return.

For the 13.5 m³ slab, the team might document a 4% project-specific allowance after reviewing conditions:

Order basis = 13.5 × 1.04 = 14.04 m³

The actual order would then follow the supplier’s permitted increment and the team’s plan for the final load. The 4% value is an example, not a default recommendation.

Plan the delivery rate

Estimate how quickly the crew and equipment can place, consolidate, finish, and test the concrete. Request truck spacing that supports continuous work without creating a queue or allowing concrete to age excessively. Consider plant travel time, traffic, pump capacity, site access, testing, weather, and any maximum discharge-time requirement in the specification.

Check every delivery ticket

  • Supplier, plant, truck, ticket number, project, and date.
  • Mixture designation and ordered quantity.
  • Batch time and arrival/discharge records required by the project.
  • Materials, admixtures, water, and other data required by the governing standard or specification.
  • Recorded water or admixture additions and authorization for any site adjustment.
  • Observed concrete condition and sampling/testing identification.

Do not add water or admixture merely to make discharge easier. Any adjustment must be permitted by the specification and supplier procedure, remain within the mixture limits, be mixed adequately, and be recorded.

Final pre-order check

  1. Approved mixture and current specification are available.
  2. Quantity calculation and project-specific allowance are independently checked.
  3. Forms, reinforcement, embeds, access, pump, crew, testing, curing, and washout are ready.
  4. Weather and contingency plans are acceptable.
  5. Supplier confirms quantity, increment, schedule, mixture, logistics, and cancellation/return terms.

See the NRMCA ordering and scheduling checklist and CCAA specifying and ordering guidance. Use the standard and terminology named by the project; the examples above do not replace supplier or specification requirements.