Underwater construction includes foundations, tunnels, pipelines, ports, offshore structures, dams, and repairs built below water level. The work is normally planned in one of two ways: create a dry working enclosure, or perform the activity in the water using specialized placement, diving, and remotely operated equipment.
Main underwater construction methods
| Method | How it works | Typical use | Main risk |
|---|---|---|---|
| Cofferdam | A temporary enclosure is installed and dewatered | Bridge piers, quay walls, foundations, and repair | Seepage, uplift, stability, flooding, and temporary-works loads |
| Caisson | A box or shaft is sunk or founded at the required level | Deep foundations, bridge piers, and marine structures | Alignment, scour, bearing level, sinking control, and worker safety |
| Tremie concrete | Concrete flows through a pipe whose outlet remains embedded in fresh concrete | Seal courses, drilled shafts, foundations, and mass placements | Washout, segregation, loss of embedment, interruption, and contaminated head |
| Precast placement | Units are fabricated in controlled conditions and installed underwater | Blocks, tunnel units, armor, pipes, and structural modules | Lifting, tolerances, joints, buoyancy, and seabed preparation |
| Diver or ROV work | Personnel or remotely operated vehicles inspect, cut, fasten, grout, or repair | Inspection, local repair, connections, and deep-water tasks | Visibility, current, entanglement, pressure, communication, and recovery |
Dewatered work versus in-the-wet work
Dewatered construction can provide conventional access and inspection, but the enclosure must resist water pressure, soil pressure, waves, current, impact, and construction loads. Pumping can cause piping, boiling, settlement, or environmental discharge problems.
In-the-wet work avoids a dry excavation but requires materials and procedures that tolerate water contact. Visibility is limited, geometry is harder to confirm, and quality control relies more heavily on instrumentation, records, divers, sonar, cameras, or ROVs.
How tremie concrete is placed
- Prepare the foundation or excavation and confirm its depth and cleanliness.
- Assemble a watertight tremie pipe and position the outlet at the starting level.
- Use a plug or other approved starting method to prevent the first concrete from mixing freely with water.
- Place concrete continuously and keep the outlet embedded in fresh concrete.
- Monitor delivered volume, concrete level, pipe embedment, placement rate, and interruptions.
- Remove contaminated or weak surface concrete where the design and procedure require it.
Key engineering risks and controls
| Risk | Typical control |
|---|---|
| Hydrostatic pressure and uplift | Design the enclosure, base seal, anchors, ballast, and pumping sequence for all stages |
| Current, waves, and scour | Use site measurements, temporary protection, monitoring, and staged work windows |
| Concrete washout or segregation | Qualified mixture, controlled flow, continuous placement, and verified tremie embedment |
| Poor visibility and geometry | Survey control, sonar or camera inspection, ROV support, and detailed placement records |
| Diving safety | Competent diving contractor, hazard assessment, communications, standby recovery, and legal compliance |
| Environmental impact | Turbidity, spill, concrete-loss, noise, habitat, and discharge controls with monitoring |
Cofferdams and caissons
A cofferdam is generally a temporary water-excluding structure, while a caisson commonly becomes part of the permanent foundation or provides a shaft used turing construction. Actual definitions and forms vary. Both require geotechnical, structural, hydraulic, temporary-works, and construction-stage design.
Quality records
Useful records include surveys, dive or ROV logs, delivery tickets, mixture test results, concrete volumes, tremie depth and embedment, interruptions, water conditions, as-built levels, integrity testing, and repair actions. Underwater work cannot rely only on a final surface inspection.